Company: | urbener |
Manager: | Raul Serrano |
Start: | July 1, 2015 |
Finish: | December 29, 2017 |
Report Date: | June 9, 2015 |
|
|
WBS | Name | Start | Finish | Work | Priority | Complete | Cost |
---|---|---|---|---|---|---|---|
1 | 001.BdD Sistema Almacenamiento Datos | Jul 1 | Jan 29 | 202d 3h | |||
1.1 | 001.01 BdD Fuentes Datos | Jul 1 | Aug 27 | 41d 5h | |||
1.1.1 | Documento identificación datos necesarios | Jul 1 | Jul 30 | 21d 5h | 0% | 7,785 | |
1.1.2 | Análisis preliminar datos: tipos, tamaños | Jul 30 | Aug 13 | 10d | 0% | 3,600 | |
1.1.3 | Análisis preliminar Gestores de Base de Datos necesarios | Aug 13 | Aug 27 | 10d | 0% | 3,600 | |
1.2 | 001.02 BdD Gestores base de datos.Diseño lógico | Aug 27 | Oct 13 | 33d 3h | |||
1.2.1 | Diseño modelos de base de datos | Aug 27 | Sep 24 | 20d | 0% | 7,200 | |
1.2.2 | Implementación prototipo | Sep 24 | Oct 13 | 13d 3h | 0% | 4,815 | |
1.3 | 001.03 BdD Sistema de Almacenamiento Diseño Físico | Sep 24 | Dec 4 | 51d 2h | |||
1.3.1 | Modelo cluster sistemas de base de datos | Sep 24 | Oct 15 | 15d 3h | 0% | 5,535 | |
1.3.2 | Implantar modelo cluster | Oct 16 | Dec 4 | 35d 7h | 0% | 12,915 | |
1.4 | 001.04 BdD Banco de pruebas | Oct 16 | Jan 29 | 76d 1h | |||
1.4.1 | Elaborar plan de pruebas-benchmark | Oct 16 | Dec 4 | 36d | 0% | 12,153.6 | |
1.4.2 | Ejecutar benchmark: validar BdD | Dec 4 | Jan 29 | 40d 1h | 0% | 13,321.5 | |
2 | 002.SCD Servicio Adquisición o Carga de Datos | Jul 1 | Mar 3 | 251d 3h | |||
2.1 | 002.01 SCD Datos Contadores | Jul 1 | Feb 4 | 149d 2h | |||
2.1.1 | Análisis documentación protocolo | Jul 1 | Jul 29 | 21d | 0% | 6,972 | |
2.1.2 | Preparación equipamiento laboratorio y pruebas | Jul 1 | Sep 7 | 48d 2h | 0% | 13,334.25 | |
2.1.3 | Diseño solución prototipo software | Oct 14 | Oct 27 | 10d | 0% | 3,600 | |
2.1.4 | Implementación solución prototipo software | Oct 29 | Dec 9 | 30d | 0% | 10,800 | |
2.1.5 | Pruebas de laboratorio sobre prototipo-maqueta | Dec 11 | Dec 24 | 10d | 0% | 2,704 | |
2.1.6 | Diseño solución integrable en SCD | Dec 25 | Jan 21 | 20d | 0% | 7,200 | |
2.1.7 | Implementar solución integrable en SCD | Jan 22 | Feb 4 | 10d | 0% | 3,600 | |
2.2 | 002.02 SCD Datos Dataloggers | Jul 1 | Sep 10 | 58d | |||
2.2.1 | Análisis documentación dataloggers | Jul 1 | Jul 2 | 2d | 0% | 720 | |
2.2.2 | Preparación equipamiento laboratorio y pruebas | Jul 1 | Jul 9 | 6d | 0% | 1,843 | |
2.2.3 | Diseño solución prototipo software | Jul 3 | Jul 9 | 5d | 0% | 1,800 | |
2.2.4 | Implementación solución prototipo software | Jul 10 | Jul 23 | 10d | 0% | 3,600 | |
2.2.5 | Pruebas de laboratorio sobre prototipo-maqueta | Jul 24 | Jul 30 | 5d | 0% | 1,380 | |
2.2.6 | Diseño solución integrable en SCD | Jul 31 | Aug 13 | 10d | 0% | 3,600 | |
2.2.7 | Implementar solución integrable en SCD | Aug 14 | Sep 10 | 20d | 0% | 7,200 | |
2.3 | 002.03 SCD Sistema cluster | Jan 22 | Mar 3 | 36d | |||
2.3.1 | Diseño lógico cluster, para SCD,SPC,SGC,SGD | Jan 22 | Feb 4 | 10d | 0% | 3,600 | |
2.3.2 | Diseño Físico cluster, para SCD,SPC,SGC,SGD | Feb 5 | Feb 18 | 10d | 0% | 3,600 | |
2.3.3 | Prototipo cluster, para SCD,SPC,SGC,SGD | Feb 19 | Mar 3 | 10d | 0% | 3,600 | |
2.3.4 | Implantar cluster SCD | Feb 19 | Feb 26 | 6d | 0% | 2,160 | |
2.4 | 002.04 SCD plan de pruebas | Feb 19 | Mar 1 | 8d | |||
2.4.1 | Elaborar plan de pruebas | Feb 19 | Feb 26 | 6d | 0% | 1,891.2 | |
2.4.2 | Ejecutar plan de pruebas: validar SCD | Feb 29 | Mar 1 | 2d | 0% | 630.4 | |
3 | 003.LNN Lógica de negocio en la nube | Mar 4 | Jun 30 | 121d | |||
3.1 | 003.01 LNN diseño y prototipado de la lógica de negocio | Mar 4 | Apr 14 | 33d | |||
3.1.1 | Diseño lógico y físco cluster LNN | Mar 4 | Mar 17 | 10d | 0% | 3,600 | |
3.1.2 | Prototipo cluster LNN | Mar 18 | Apr 14 | 20d | 0% | 7,200 | |
3.1.3 | Implantar cluster LNN | Mar 4 | Mar 8 | 3d | 0% | 1,080 | |
3.2 | 003.02 LNN interfaces de conexionado y metodos de la lógica de negocio | Mar 4 | Jun 28 | 83d | |||
3.2.1 | Validar requisitos y especificaciones: modelo conceptual | Mar 4 | Mar 17 | 10d | 0% | 3,600 | |
3.2.2 | Diseño lógico y físco interfaces y métodos | Mar 18 | Apr 14 | 20d | 0% | 7,200 | |
3.2.3 | Desarrollo interfaces y métodos | Apr 15 | Jun 23 | 50d | 0% | 18,000 | |
3.2.4 | Despliegue en nube LNN | Jun 24 | Jun 28 | 3d | 0% | 1,080 | |
3.3 | 003.03 LNN plan de pruebas | Jun 24 | Jun 30 | 5d | |||
3.3.1 | Elaborar plan de pruebas | Jun 24 | Jun 28 | 3d | 0% | 1,012.8 | |
3.3.2 | Ejecutar plan de pruebas: validar LNN | Jun 29 | Jun 30 | 2d | 0% | 585.6 | |
4 | 004.SPC Sistema Previsión Consumo | Jul 1 | Nov 8 | 169d | |||
4.1 | 004.01 SPC inteligencia artificial: fuentes de datos necesarios | Jul 1 | Jul 28 | 25d | |||
4.1.1 | Requisitos de información necesaria: meteo, etc. | Jul 1 | Jul 7 | 5d | 0% | 1,800 | |
4.1.2 | Análisis integración fuentes de datos | Jul 1 | Jul 14 | 10d | 0% | 3,600 | |
4.1.3 | Integración fuentes datos en BdD | Jul 15 | Jul 28 | 10d | 0% | 3,600 | |
4.2 | 004.02 SPC algoritmos del sistema de IA | Jul 15 | Oct 26 | 74d | |||
4.2.1 | Definición algoritmos | Jul 15 | Aug 25 | 30d | 0% | 10,800 | |
4.2.2 | Desarrollo algoritmos en sistema clusterizable SPC | Aug 26 | Oct 20 | 40d | 0% | 14,400 | |
4.2.3 | Implantación en cluster SPC | Oct 21 | Oct 26 | 4d | 0% | 1,440 | |
4.3 | 004.03 SPC interfaces de conexión con el resto de componentes del sistema | Jul 1 | Oct 26 | 61d | |||
4.3.1 | Interfaz conexión LNN | Aug 26 | Aug 31 | 4d | 0% | 1,440 | |
4.3.2 | Interfaz conexión IA | Oct 21 | Oct 26 | 4d | 0% | 1,440 | |
4.3.3 | Desarrollo software | Jul 1 | Sep 8 | 50d | 0% | 18,000 | |
4.3.4 | Implantar cluster SPC | Jul 1 | Jul 5 | 3d | 0% | 1,080 | |
4.4 | 004.04 SPC plan de pruebas | Oct 27 | Nov 8 | 9d | |||
4.4.1 | Elaborar plan de pruebas | Oct 27 | Nov 3 | 6d | 0% | 2,025.6 | |
4.4.2 | Ejecutar plan de pruebas: validar SPC | Nov 4 | Nov 8 | 3d | 0% | 878.4 | |
5 | 005.SGC Sistema de Gestion de Compra | Nov 9 | Jan 12 | 97d | |||
5.1 | 005.01 SGC interfaces de conexión con el resto de componentes | Nov 9 | Nov 22 | 20d | |||
5.1.1 | Interfaz SPC | Nov 9 | Nov 22 | 10d | 0% | 3,600 | |
5.1.2 | Interfaz SVAD | Nov 9 | Nov 22 | 10d | 0% | 3,600 | |
5.2 | 005.02 SGC interfaz de conexión con OMIE | Nov 9 | Dec 20 | 30d | 0% | 10,800 | |
5.3 | 005.03 SGC Desarrollo Software | Nov 9 | Jan 5 | 42d | |||
5.3.1 | Diseño Lógico y Físico | Nov 9 | Nov 22 | 10d | 0% | 3,600 | |
5.3.2 | Desarrollo | Nov 23 | Jan 3 | 30d | 0% | 10,800 | |
5.3.3 | Implantar Cluster SGC | Jan 4 | Jan 5 | 2d | 0% | 720 | |
5.4 | 005.04 SGC Plan de Pruebas: validar SGC | Jan 6 | Jan 12 | 5d | 0% | 1,464 | |
6 | 006.SGD Servicio de Gestión de Desvíos | Jan 13 | Mar 29 | 66d | |||
6.1 | 006.01 SGD interfaces de conexión SGC y dataloggers | Jan 13 | Feb 9 | 20d | 0% | 6,752 | |
6.2 | 006.02 SGD Desarrollo Software | Feb 10 | Mar 23 | 42d | 24,192 | ||
6.2.1 | Diseño Lógico y Físico | Feb 10 | Feb 23 | 10d | 0% | 3,600 | |
6.2.2 | Desarrollo | Feb 10 | Mar 23 | 30d | 0% | 10,800 | |
6.2.3 | Implantar cluster SGD | Feb 10 | Feb 13 | 2d | 0% | 720 | |
6.3 | 006.03 SGD Plan de Pruebas: validar SGD | Mar 24 | Mar 29 | 4d | 0% | 1,171.2 | |
7 | 007.SVAD Sistema Virtual Ayuda a la Decisión | Apr 15 | Jul 7 | 60d | 0% | 21,600 | |
8 | 008.APL Aplicativo Cliente | Mar 30 | Dec 29 | 705d 7h | |||
8.1 | 008.01 APL aplicación android | Mar 30 | Oct 31 | 154d | 0% | 55,440 | |
8.2 | 008.02 APL aplicación IOS | Mar 30 | Nov 16 | 166d | 0% | 59,760 | |
8.3 | 008.03 APL aplicación web | Mar 30 | Dec 19 | 188d 7h | 0% | 67,995 | |
8.4 | 008.04 APL aplicación escritorio | Mar 30 | Dec 29 | 197d | 0% | 70,920 | |
9 | 009.ADM Administración juridico | Jul 1 | Dec 29 | 652d 4h | 0% | 234,900 | |
10 | Equipos y Estructuras | Jul 1 | Dec 29 | 5223d 4h | |||
10.1 | BdD | Jul 1 | Dec 29 | 1306d | |||
10.1.1 | Nodo 1 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.1.2 | Nodo 2 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.2 | LNN | Jul 1 | Dec 29 | 1306d | |||
10.2.1 | Nodo 1 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.2.2 | Nodo 2 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.3 | Cluster | Jul 1 | Dec 29 | 1306d | |||
10.3.1 | Nodo 1 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.3.2 | Nodo 2 | Jul 1 | Dec 29 | 653d | 0% | 10,448 | |
10.4 | SVAD | Jul 1 | Dec 29 | 653d | 0% | 52,240 | |
10.5 | Dataloggers | Jul 1 | Dec 29 | 652d 4h | 0% | 52,205 |
Name | Short name | Type | Group | Cost | |
---|---|---|---|---|---|
Administración Juridico | AJ | Work | 45 | ||
Analista Programador 1 | AP1 | Work | 45 | ||
Analista Programador 2 | AP2 | Work | 45 | ||
Arquitecto BdD | ABD | Work | 45 | ||
Arquitecto Sistemas | ASS | Work | 45 | ||
Arquitecto Software | AS | Work | 45 | ||
Experto IA | EIA | Work | 45 | ||
Jefe Proyecto | JP | Work | 45 | ||
Programador Android | PA | Work | 45 | ||
Programador Apl. web | PAW | Work | 45 | ||
Programador IOS | PIOS | Work | 45 | ||
Técnico Instalaciones Eléctricas | TIE | Work | 31 | ||
Técnico Sistemas | TS | Work | 45 | ||
Usuario Probador | UP | Work | 31 | ||
Usuario Validador | UV | Work | 31 | ||
Dataloggers | DLS | Material | 10 | ||
Hardware SVAD | HVA | Material | 10 | ||
Servidor Cloud 1 | VPS1 | Material | 2 | ||
Servidor Cloud 2 | VPS2 | Material | 2 | ||
Servidor Cloud 3 | VPS3 | Material | 2 | ||
Servidor Cloud 4 | VPS4 | Material | 2 | ||
Servidor Cloud 5 | VPS5 | Material | 2 | ||
Servidor Cloud 6 | VPS6 | Material | 2 |